+90 216 706 15 18 hi@cormind.com

What Is Cycle Time and How Is It Calculated?

cycle time

Efficiency is one of the most critical factors determining competitiveness in production processes. At this point, cycle time stands out as a key performance indicator that measures the time from the start to the completion of a product or process. Accurately calculating cycle time enables companies to optimize production planning, improve resource utilization, and sustainably increase operational efficiency.

What Is Cycle Time

Cycle time refers to the total time elapsed from the beginning to the end of a production process. In other words, it is the time it takes for a workstation to complete a product and move on to the next one. Used in many fields from manufacturing to services, this concept is a fundamental performance metric that shows how efficiently processes operate.
In production environments, cycle time covers the period from the moment a product enters the line until it is completed. This includes all stages such as setup, processing, assembly, quality control, and packaging. Short cycle times indicate balanced processes and efficient resource use. Long cycle times signal issues such as bottlenecks, unplanned downtime, or operational inefficiency.
Measuring cycle time correctly is a critical step for understanding production performance, identifying bottlenecks, and spotting improvement opportunities. Therefore, in production management, cycle time is evaluated not only as a time measure but also as an indicator of quality and efficiency.

What Is the Difference Between Takt Time and Cycle Time

Takt time and cycle time are two critical concepts frequently used together in production planning. Both express the time dimension of a production process; however, they represent different values.

Takt time shows the ideal production pace the line must achieve to meet customer demand. The process should progress at a tempo aligned with demand. When calculating takt time, the total available production time is divided by customer demand, resulting in the target production time per unit.

Cycle time is the actual time the production line spends to complete a unit. It is affected by variables such as machine performance, labor efficiency, material flow, and equipment setup times.

The difference can be summarized as follows:

  • Takt time shows the planned speed.
  • Cycle time expresses the actual speed.

If the cycle time is shorter than the takt time, the line can meet customer demand. If cycle time exceeds takt time, delays occur in the plan. For this reason, production managers analyze both values together to assess how balanced the line operates.

Cycle Time Calculation

Cycle time is calculated by dividing the total production time by the number of units produced. This is one of the most basic methods to understand the average performance of a line and to evaluate efficiency.

Formula:

Cycle Time = Total Production Time ÷ Number of Units Produced

When calculating, include the time spent in every stage of production. These stages cover steps such as setup, processing, loading, unloading, inspection, or waiting. The total time obtained is divided by the number of units completed during the period to find the average cycle time.

Cycle Time Calculation Steps

  1. Identify the durations of all steps in the process.
  2. Determine the number of units completed in the same process.
  3. Divide total production time by the number of units to calculate average cycle time.
See Also:  Human + AI: Building Hybrid Decision Systems in Production

Example Calculation

Suppose the following times are measured for a single unit on a line:

  • Processing time, 60 seconds
  • Setup time, 10 seconds
  • Loading and unloading time, 5 seconds

Total production time in this case:

Total Time = 60 + 10 + 5 = 75 seconds

If 1 unit is produced in this process.

Cycle Time = 75 seconds ÷ 1 unit = 75 seconds

According to this calculation, it takes 75 seconds for the line to complete one unit.

Cycle Time Examples and Calculation Methods

Cycle time varies according to machine types, production methods, and materials used. Each method determines cycle time with its own parameters.

Plastic Injection Cycle Time Calculation

Plastic injection cycle time is the total time required to produce a single plastic part in a mold. It usually consists of four main stages.

  • Mold closing time
  • Injection time
  • Cooling time
  • Mold opening time

Formula:

Cycle Time = Mold Closing Time + Injection Time + Cooling Time + Mold Opening Time.

Example:

If mold closing is 15 seconds, injection is 30 seconds, cooling is 60 seconds, and mold opening is 10 seconds.

Cycle Time = 15 + 30 + 60 + 10 = 115 seconds

Thus, the total cycle time for one plastic part is 115 seconds.

Shearing or Slitting Machine Cycle Time Calculation

In shearing or slitting operations, cycle time is the time it takes for a metal sheet or profile to pass through the machine. The sheet is processed with rotating blades or cutting tools.

Formula:

Cycle Time seconds = Metal Thickness mm ÷ Blade Thickness mm × 1 ÷ Blade Speed mm per second

Example:

If a 1 mm sheet is processed with 0.5 mm blades at 50 mm per second, [complete the sentence].

Cycle Time = 1 ÷ 0.5 × 1 ÷ 50 = 0.2 seconds

The sheet passes through in 0.2 seconds.

Calculating Cycle Time with Multiple Product Types

On lines producing different product variants, cycle times may differ. This can affect line balance. Therefore, each product’s cycle time should be determined, and the process balanced.

Possible methods for efficiency:

  • Sort products by cycle time.
  • Resequence production order.
  • Increase equipment capacity.

The goal is to balance production speeds of different items and optimize the overall line cycle time.

Injection Molding Machine Cycle Time Formula

In injection molding machines, cycle time varies by material type, mold design, and machine capacity. It directly affects production efficiency.

Formula:

Cycle Time seconds = Setup Time + Melting Time + Holding or Packing Time + Cooling Time

Example:

If the setup is 10 seconds, melting is 20 seconds, holding is 30 seconds, and cooling is 40 seconds.

Cycle Time = 10 + 20 + 30 + 40 = 100 seconds

This is the total time needed to produce one plastic part.

Milling Machine Cycle Time Calculation

On milling machines, cycle time is determined by the properties of the material, the condition of the cutting tool, and speed parameters.

Formula:

Cycle Time seconds = Setup Time seconds + Machining Time seconds

The main factors that affect machining time include cutting speed, tool change frequency, and workpiece dimensions. Regular maintenance and proper tool selection optimize cycle time.

Assembly Line Balancing Cycle Time Calculation

On assembly lines, cycle time is the time it takes for a unit to move from one station to the next. The aim is to complete tasks at each station in as equal a time as possible.

Formula:

Cycle Time seconds = Longest Assembly Time seconds ÷ Number of Parts on the Line

When assembly times are balanced, waiting decreases, line efficiency increases, and production flow becomes continuous.

Improvement Methods:

  • Resequence assembly steps
  • Combine operations
  • Increase equipment capacity

Cycle Time in Automotive Assembly Lines

In automotive assembly, cycle time is the time a vehicle takes to move from one station to another. This measurement determines the overall capacity of the line.

Example:

If a car advances to the next station every 25 seconds, and the plant runs 8 hours a day.

See Also:  What is ERP?

Formula:

Daily Output units per day = Line Rate units per second × Working Time seconds per day

Daily Output = 1 ÷ 25 × 8 × 60 × 60 = 115.2, approximately 120 vehicles per day

This shows the line can produce about 120 cars per day.

Planer and Thicknesser Cycle Time

On planers and thicknessers, cycle time varies by workpiece thickness, depth of cut, and speed parameters.

Formula:

Machining Speed mm per second = Material Removed mm ÷ Machining Time seconds

Example:

If a 100 mm thick metal plate is reduced by 5 mm, and the operation takes 15 seconds.

Machining Speed = 5 ÷ 15 = 0.33 mm per second

This shows an average removal rate of 0.33 mm per second.

PLC Cycle Time

PLC cycle time is the time it takes for a command to be processed and converted into an output in a control system. It determines response speed and is critical in automation. PLC cycle time typically ranges from 1 to 10 microseconds. This varies with system complexity, processor speed, and program size. A low cycle time means faster response and higher stability. Therefore, PLC cycle time is carefully considered in automation design.

Factors That Affect Cycle Time

Cycle time varies based on many components of the process. Careful analysis helps identify bottlenecks and improve efficiency.

Machine Performance

The technical capacity, maintenance history, and operating efficiency of machines are among the most critical determinants of cycle time. Poor maintenance or worn parts reduce speed and cause unplanned downtime. High-performance machines shorten processing time and reduce cycle time. Regular maintenance plans, sensor-based condition monitoring, and early fault detection are crucial.

Operator Skill

The human factor directly affects performance. Operator experience, equipment knowledge, and process awareness play a decisive role in shortening cycle time. Trained operators use machines optimally, detect errors quickly, and intervene effectively. Inexperienced or insufficiently trained staff can slow processes and increase errors. Regular technical training and performance tracking are critical.

Material Quality

The quality of raw materials directly affects production flow. Low-quality materials may extend processing time, require extra checks, or increase maintenance needs. High-quality materials support stable machine operation and shorter process times. This also protects product quality and raises customer satisfaction.

Level of Automation

The degree of automation determines how fast and efficiently progress is made. Manual steps vary with operator speed and attention. Automated systems run at a standard pace, error-free and uninterrupted, which reduces cycle time. Using robotics, sensor-based controls, and data-driven software stabilizes line performance, increases speed, and improves predictability.

Data Management

Data collection and analysis play a strategic role in improving cycle time. Without regular analysis, bottlenecks remain unnoticed and performance losses occur. Real-time monitoring reveals fluctuations in equipment performance and slowdowns immediately. Planning becomes healthier, failure risk decreases, and overall cycle time is optimized.

Strategies to Reduce Cycle Time

Shortening cycle time is one of the most effective ways to increase efficiency. Shorter times raise capacity, lower costs, and enable faster response to demand.

Use of Automation and Robotics

Automating repetitive manual tasks is highly effective for increasing speed. Automation eliminates human error and runs processes at a standard pace. This clearly reduces cycle time, especially on assembly lines and high-volume environments. Integrating robotics stabilizes operation durations and keeps the flow continuous. Robotics also reduces physical load on workers, improving safety and stability.

Real Time Data Monitoring

Real-time tracking is critical for control and optimization. Data from sensors and monitoring systems instantly show machine performance, workstation congestion, and waiting times. When analyzed regularly, this data reveals bottlenecks, at-risk equipment, and slow operations. Live visibility makes in-line balancing easier and lowers total cycle time.

Line Balancing

Balancing task times across stations directly affects cycle time. If workloads are uneven, waiting occurs, and overall speed drops. To balance the line, steps can be rearranged, operations combined, or equipment capacity increased. This improves flow, removes idle time, and synchronizes stations.

Predictive Maintenance

Machine failures and unplanned stops are common causes of long cycle times. Predictive maintenance continuously monitors performance and anticipates faults. Sensor data such as vibration, temperature, or energy use are analyzed for anomalies. Early intervention schedules maintenance proactively, so the line keeps running. Production continuity is preserved, and cycle time remains consistently low.

AI-Based Planning

AI-supported planning analyzes historical data, identifies inefficiencies, and creates the best sequence. These systems evaluate many parameters, from operator performance to equipment utilization. AI algorithms automatically optimize task allocation, balance workload, and minimize time loss. This is especially valuable in complex lines, as it improves planning accuracy and keeps cycle time under continuous control.

Check out other articles: